Classic Case

    详细说明

    Project Name: Gansu Xingye Minqin 48.5MW Photovoltaic Power Generation Project
    Project cycle: Starting from December 2021 and ending in January 2022.
    Project scope:
    This project includes a power prediction system, fault recording system, AGC/AVC control system, primary frequency regulation system, electric energy metering system, electric energy quality management, secondary security system, communication system, active power stability control system, and panoramic monitoring system for the 110kV booster station of Xingye Minqin Photovoltaic Power Station.
    Project achievements:
    The Gansu Xingye Minqin 48.5MW Photovoltaic Power Generation Project is located in Minqin County, Wuwei City, Gansu Province. The total planned installed capacity of this project is 48.5MW, all of which are monocrystalline silicon solar modules. For the second phase of capacity expansion project.
    This project covers the core systems of new energy power plants such as comprehensive automation, secondary security, and safety and stability. The construction period of the project is short, and the installation and commissioning tasks are tight. However, with the cooperation of the owner, construction party, and design party, Odewete successfully completed the grid connection task by means of early delivery, compressed commissioning period, task merging, etc., and received unanimous praise from the owner and the power grid company.
    The uniqueness of this project lies in the first operation of a panoramic monitoring system in the northwest region. The panoramic monitoring system consists of safety and stability, emergency status, oscillation monitoring, source control terminals, etc. It is an integrated system that integrates power automation, safety and stability, and power monitoring.
    The panoramic monitoring system was independently designed, produced, and debugged by Odewete. The design, construction, and testing plans were reviewed by the Gansu Provincial Company and successfully connected to the grid for operation.